You enter through security, then reach the data hall, a big room of racks. Each rack holds servers and the network cables that link them. Power reaches the rack through switchgear, a UPS and a PDU, with a generator as backup, while cooling carries away the heat the computers make.

On this page

The picture

Think of a big grocery store. Shoppers use the front door. Staff use the back. Long rows of shelves hold the goods. A cooling plant keeps the food cold, and a generator keeps the lights on in a storm.

A data center has the same parts, with computers as the goods. One twist: in a store, cold protects the food. In a data center, cooling carries away the heat the computers make.

The front door

Security starts at the door, and the big operators describe it in public.

  • Amazon says professional security staff control its building entrances, staff use multi-factor authentication, visitors are signed in and escorted, and cameras record the access points to server rooms.1
  • Microsoft says its datacenter entrance is staffed with security officers and the datacenter floor can only be entered with prior approval and a full body metal detection screening. It says visitors must hand back their temporary badges on the way out.2
  • Google says it uses biometric identification, metal detection, cameras, vehicle barriers and laser-based intrusion detection to protect its data center floors.3

Sites differ. Your employer sets the rules for yours.

The data hall

Past security is the data hall, the big room that holds the computers. It is laid out in long rows of racks with aisles between them. Some halls have a raised floor, with space underneath for cables or cool air. Others run cables overhead.

The aisles are not all alike. The Department of Energy (DOE) design guide describes a common layout. Racks sit in rows, back to back. Equipment pulls cool air in from cold aisles in front of it and pushes heat out into hot aisles behind it.4

So is a cold aisle icy? No. The guide recommends keeping the air at the server intakes between 65°F and 80°F.4

A rack

A rack is a tall metal frame. Servers slide into it one above another, like books on a shelf. Slots are measured in rack units, written U. One server may take 1U, 2U or more.

Empty slots get blank panels, which are flat covers. The DOE guide says to block vacant slots on the intake side of the rack so hot air cannot loop back.4

A server

A server is a computer built to sit in a rack. It has no screen. Fans pull air in at the front and push it out the back, which the DOE guide calls front-to-back airflow.4

Servers have parts that wear out, such as drives, fans, memory and power supplies. For what a data center technician does about that, read the role page. It lists the duties employers post.

Network cables

Servers talk to each other and to the internet through cables. Copper cables carry electric signals. Fiber cables carry light through thin glass strands.

Cables plug into network switches. A switch is a box that passes signals between many devices. A patch panel gathers many cable ends in one place so they are easy to find. The fiber network technician page covers the cabling job.

Neat cables matter for more than looks. The DOE guide says cable congestion in raised-floor spaces can sharply reduce the total airflow, and that removing abandoned or dead cables helps the cooling system deliver air.4

Power from the street to the rack

The DOE guide says a data center typically has a power path made of utility service, a switchboard, switchgear, a backup generator, and multiple UPS and PDU units for redundancy.4 Here is a simple picture of the trip from the street to a server. Real sites differ.

  1. Utility service. The power company’s line from the street.
  2. Switchboard and switchgear. Large cabinets of breakers and controls that route and protect the power.
  3. UPS. The uninterruptible power supply, described below.
  4. PDU. A power distribution unit, a box that splits power into many outlets. Some stand on the floor.
  5. Rack power strip. A strip inside the rack, often called a rack PDU, feeds each server.

Power-side jobs have their own role pages: the data center electrician, the electrical engineer and the substation and high-voltage technician.

Backup power

ENERGY STAR says a UPS protects connected equipment from power outages. In a data center, it gives operators a chance to bring on backup generators.5 A generator is an engine that makes electricity.

The DOE guide says a UPS can be built on battery banks, rotary machines, fuel cells or other technologies.4 The UPS and battery technician page covers the batteries side of the work.

Redundancy means extra units, so one can fail or be serviced without a shutdown. Uptime Institute says a Tier III data center is concurrently maintainable and needs no shutdowns when equipment is serviced or replaced.6 Amazon says its electrical power systems are designed to be fully redundant and maintainable without impact to operations.1

Safety is not optional. OSHA’s lockout/tagout standard requires employers to set up a program for locking and tagging the devices that isolate energy, so equipment cannot start up unexpectedly while someone works on it.7 This lesson gives no steps for any task. Follow your employer’s written procedure every time.

Cooling

Computers make heat. Cooling carries it away. Designs differ a lot. The DOE guide describes these common ideas:

  • Air conditioners. CRAC units are computer room air conditioners. The guide says packaged units like these are likely the most common cooling equipment in smaller data centers.4
  • Chilled water. A chiller makes cold water, and pipes carry it to air handlers, called CRAH units. The guide points large facilities to water-cooled chillers in a central chilled water plant, and names cooling towers as one way for water-cooled systems to reject heat.4
  • Outside air. An air-side economizer brings in outside air whenever it is cooler than the air returning from the room and the humidity is acceptable.4
  • Liquid cooling. Liquid carries the heat away. The guide says some liquid-cooled setups remove practically all the heat without any fans.4

The HVAC and mechanical technician page covers the cooling job. Building controls have their own: the controls and BMS technician.

Next

Sources

  1. AWS: Data Center - Our Controls, read 2026-11-28. ↩ ↩2

  2. Microsoft: Datacenter physical access security, read 2026-11-28. ↩

  3. Google Cloud: Google infrastructure security design overview, read 2026-11-28. ↩

  4. DOE: Best Practices Guide for Energy-Efficient Data Center Design, read 2026-11-28. ↩ ↩2 ↩3 ↩4 ↩5 ↩6 ↩7 ↩8 ↩9 ↩10 ↩11

  5. ENERGY STAR: Uninterruptible Power Supplies, read 2026-11-28. ↩

  6. Uptime Institute: Tier Classification System, read 2026-11-28. ↩

  7. eCFR: 29 CFR 1910.147, The control of hazardous energy (lockout/tagout), read 2026-11-28. ↩

Frequently asked questions

Is it easy to walk into a data center?

No. The big operators describe layers of security. Amazon says professional security staff control the building entrances, visitors are signed in and escorted, and cameras record access to server rooms. Microsoft says the datacenter floor needs prior approval and a full body metal detection screening. Google lists biometric identification, metal detection, cameras, vehicle barriers and laser-based intrusion detection.

[1] AWS: Data Center - Our Controls · read [2] Microsoft: Datacenter physical access security · read [3] Google Cloud: Google infrastructure security design overview · read

What is a rack?

A rack is a tall metal frame that holds equipment. Servers slide into it one above another, like books on a shelf. Network switches and power strips mount in racks too. Rows of racks fill the data hall, with aisles between the rows.

What is the difference between a hot aisle and a cold aisle?

In the layout the U.S. Department of Energy describes, racks sit in rows back to back. Equipment pulls cool air in at the front from the cold aisle and pushes warm air out the back into the hot aisle. The guide says to block empty rack slots on the intake side so hot air does not loop back.

[1] DOE: Best Practices Guide for Energy-Efficient Data Center Design · read

Why do data centers keep cables so neat?

Neat cables are easier to trace and fix. They also protect airflow. The Department of Energy guide says cable congestion in raised-floor spaces can sharply reduce the air that gets through, and that removing abandoned or dead cables helps the cooling system deliver air.

[1] DOE: Best Practices Guide for Energy-Efficient Data Center Design · read

What is a UPS?

UPS stands for uninterruptible power supply. ENERGY STAR says it protects connected equipment from power outages, and that in a data center it gives operators a chance to bring on backup generators. The Department of Energy guide says UPS systems can run on battery banks, rotary machines, fuel cells or other technologies.

[1] ENERGY STAR: Uninterruptible Power Supplies · read [2] DOE: Best Practices Guide for Energy-Efficient Data Center Design · read

How are data centers cooled?

Designs differ a lot, and a site may mix methods. The Department of Energy guide covers packaged air conditioners called CRAC units, chilled-water systems with a central plant of water-cooled chillers, outside air when it is cooler than the air coming back from the room, and liquid cooling.

[1] DOE: Best Practices Guide for Energy-Efficient Data Center Design · read

Related roles

Data center electrician: build and run the power systems

Data center electricians build and run the power systems: Crusoe's Master Electrician runs projects, EdgeConneX operations staff run switchboards, generators and UPS. Google’s Data Center Facilities Technician II, Electrical posting in Reno NV lists $105,000 to $145,000, plus a 15% bonus target, equity and benefits. [1] Crusoe posting, Field Master Electrician (Remote US) · read [2] EdgeConneX posting, Atlanta GA · read [3] Google posting, Reno NV · read

Explore this job